Gas turbine delivery slots at the major manufacturers are booked into 2029, and lead times for new heavy-duty units now run roughly five years. Demand for power is not waiting. The U.S. Energy Information Administration forecasts U.S. electricity load growth of 1.9 percent in 2026 and 2.5 percent in 2027, with ERCOT averaging near 10 percent annual growth across that span. Because new generating capacity cannot arrive on that schedule, utilities and industrial operators are keeping the machines they already own in service.
That decision lands in the coil room.
Life extension turns into rewind work
A generator or a large mill motor that cannot be replaced gets rewound. A rewind on a large machine is not a spool of round wire. It is a set of form coils, each cut to length from copper strip, edgewound or looped, formed to a specific slot and knuckle geometry, taped to a controlled overlap, and pressed to dimension. One machine can absorb several hundred coils and weeks of bench time.
Shops that quoted this work at four to six weeks in 2023 are quoting longer today. The limiting factor is rarely order intake. It is generator coil rewind capacity inside the building — how many finished coils the bench can produce per week without drifting out of tolerance.
Where the hours actually go
Ask a coil shop foreman where a large rewind loses time and taping comes up first. Hand taping a large form coil is slow, and overlap consistency varies by operator and by hour of the shift. Forming is second. A coil formed slightly out of geometry gets reworked or scrapped, and on a large machine that scrap carries serious material value — a problem record copper prices have made considerably worse.
Pressing and curing add fixed hours that overtime cannot shorten. Adding a shift moves the bottleneck rather than removing it.
The workforce math is not improving

The people who can hand-form and hand-tape a large stator coil are frequently the same people who have been doing it since the 1990s. Output is climbing while bench headcount stays flat. Federal Reserve figures released in July 2026 put manufacturing capacity utilization at 75.7 percent for June, with industrial production growing at a 4.0 percent annual rate during the second quarter. Rising volume on a static workforce pushes shops toward equipment that holds a process without a specialist standing over it.
What shops are actually buying
Three purchases repeat across this cycle:
- Automatic taping machines that hold a set overlap across the full coil, including the knuckle
- Forming machines that repeat a geometry from a stored setup rather than a scribed template
- Cut-to-length and edgewinding equipment that improves strip yield before a coil is ever formed
Connection and distribution work is following the same path, as bus bar insulation taping volume rises alongside new generation.
Planning around a five-year turbine wait
Generator coil rewind capacity is now a scheduling question for asset owners, not only for coil shops. A plant that intends to run a machine another eight years needs a shop that can turn the rewind in a predictable window. Shops that want that work are automating the two processes that set their throughput ceiling — forming and taping — while the order book supports the investment.
CAM Innovation: Custom Machinery for Motor and Coil Manufacturing
CAM Innovation builds custom automated machinery for the electric motor and coil manufacturing industry from Hanover, Pennsylvania. Every machine is Made in USA and designed around the process the customer actually runs.
Our Equipment Includes:
- Service — Parts and field support for machines that stay in production
- DC Motor Equipment — Undercutters, banding machines, TIG welders, and multi-process commutator machines
Automating a process?
Contact CAM Innovation to discuss your part, your volume, and your shop layout.
Works Cited
- Board of Governors of the Federal Reserve System. “Industrial Production and Capacity Utilization — G.17.” Federal Reserve, 17 July 2026, https://www.federalreserve.gov/releases/g17/current/default.htm.
- U.S. Energy Information Administration. “Fossil Generation Could Rise with Faster-Than-Expected Growth in Data Center Power Demand.” Today in Energy, U.S. Department of Energy, 12 Mar. 2026, https://www.eia.gov/todayinenergy/detail.php?id=67344.